| Timeline |
|
| May 1, 2006 |
Lake Powell Pipeline Development Act |
| October, 2006 |
Project manager chosen for Preliminary Engineering and Environmental Studies phase. |
| February, 2007 |
MWH Americas, Inc selected to perform Preliminary Engineering and Environmental Studies. |
|
|
|
| March 2008 |
Begin FERC Licensing and NEPA compliance
|
| 2012 |
Licenses, Permits, ROD issued |
| 2013 |
Final design begins
|
| 2015 |
Construction begins |
| 2020 |
Water delivery begins |
|
|
|
|
|
|